So now we have to wait for the floor to be reinforced and then we need the framing to be reinspected. After that, the HVAC can be inspected (the permit has finally been reissued), and the natural gas can be roughed in for the stove and barbecue. With all the delays, we're now expected to get into the house to start painting by mid-March.
While all the big work has been mostly stalled, a couple smaller projects got completed. We finally have the right 16' window installed. I have also spent the last couple weekends screwing down all the floorboards (~2200 screws!) to address all the loose and squeaky spots.
Still no pictures since nothing has changed in how the house looks.